How to Create a Work Order and Job Cards

In short

Go to Manufacturing → Work Orders → Create Work Order, enter the product, planned quantity and operations, and save. Release to Production creates a job card for each operation; each job card goes Start → Submit for QC → QC Pass or QC Fail.

Key facts
WhereManufacturing → Work Orders, Production → Job Cards
Steps6

Step by step

  1. 1

    Create the work order

    Go to Manufacturing → Work Orders and click Create Work Order. Enter Product Name and Planned Quantity (required), and choose the Project — needed for job cards to be created on release — plus BOM, Work Center, scheduled dates, Status and Priority.

  2. 2

    Add operations

    On the Operations tab add each operation with Operation Name and Planned Qty, and optionally Planned Duration (min) and Assigned To.

  3. 3

    Save

    Click Create Work Order.

  4. 4

    Release to production

    Open the work order and click Release to Production. It moves to In Progress and a job card is created for each operation.

  5. 5

    Work the job cards

    In Production → Job Cards each card goes Start → Submit for QC → QC Pass (completed) or QC Fail (rejected).

  6. 6

    Finish

    Click Mark Done on the work order when all operations are complete.

Common questions

Why were no job cards created when I released the work order?

Job cards are created on release only when the work order has a Project and at least one operation on its Operations tab. Add them and release again.

What are the job card statuses?

A job card is started, then submitted for QC, and ends as QC Pass (completed) or QC Fail (rejected). That record shows who did each operation and how it ended.

Can I create a job card without a work order?

Yes. Production → Job Cards → New Job Card lets you create one directly for a project and equipment, with quantity and planned dates.